St. Landry Parish road work notice
As part of the St. Landry Parish Smooth Ride Home rural road improvement program, the following is the work schedule for Tuesday through Saturday, weather permitting:
Phase 1A and 2A:
- The contractors will continue to pave for the next three to four days on Chretien Point Road Once finished they will move to Begnaud Road.
- Pre-construction pipe work will begin on Oak Roadand continue on into the Lewisburg area. Most of the pipe replacements are small diameter pipes so the crew is working on multiple locations throughout each day.
Phase 1B
Tuesday through Friday: St. Mary Road: Pre-construction pipe work.
Tuesday: School Road- lay asphalt.
Wednesday: Babineaux Road - lay asphalt.
Thursday through Saturday: Duplechain Road- lay asphalt.